datetime - Java Time: Get max number of weeks for particular year

I only found a solution for Joda Time.

My solution works only if the last day is not in the first week:

LocalDate.now() // or any other LocalDate
  .withDayOfMonth(31)
  .withMonth(12)
  .get(weekFields.weekOfWeekBasedYear())

So what is the correct way in Java Time (like in Joda Time)?

See Question&Answers more detail:os

与恶龙缠斗过久,自身亦成为恶龙;凝视深渊过久,深渊将回以凝视…
Welcome To Ask or Share your Answers For Others

1 Reply

0 votes
by (71.8m points)

This information is available directly using the java.time.* API.

The key method is rangeRefinedBy(Temporal) on TemporalField. It allows you to obtain a ValueRange object that provides the minimum and maximum values for the field, refined by the temporal object passed in.

To find out how many ISO weeks there are in the year, do the following:

LocalDate date = LocalDate.of(2015, 6, 1);
long weeksInYear = IsoFields.WEEK_OF_WEEK_BASED_YEAR.rangeRefinedBy(date).getMaximum();
System.out.println(weeksInYear);

Note that the date you pass in is used to determine the answer. So when passing in dates in early January or late December ensure you understand how the ISO week-based calendar works, and the difference between the calendar year and the week-based year.