Its always better to include what all you have tried and tested out.
Step1: create a CYCLE and then Extended Calendar
cycle: YEARLY_JAN
start_date: 01/01/1972
end_date: 01/05/1972
1972 indicates for all future years
extended_calendar: FIRST_DAY_JAN
workday:
non_workday:
holiday: S
holcal:
cyccal: YEARLY_JAN
adjust:
condition: MNTHD#1
MNTHD#1 indicates first date of the month
Step2: Use the calendar in exclude_calendar attribute for the required job
update_job: BATCH_JOB_TO_UPDATE
exclude_calendar: FIRST_DAY_JAN