I'm trying to create new project sheets in a folder, however I can't find a way to ensure the sheet is a project sheet.
Here is my code so far:
def create_resource_sheet(name):
""" Create a new resource sheet.
:param name:
:return:
"""
folder_id = get_resource_folder_id()
# TODO: Find and delete existing sheet with this name
resource_sheet = SS.models.Sheet({
'name': name,
# 'gantt_enabled': True, # This was added as an attempt to force it to a project sheet, but error 1032
'columns': [{
'title': 'Task',
'type': 'TEXT_NUMBER',
'primary': True,
'width': 200
}, {
'title': 'Status',
'type': 'PICKLIST',
'options': ['wtg', 'hld', 'ip', 'rdy', 'rev', 'fin', 'omt'], # TODO: Update this list
'width': 180
}, {
'title': '% Complete',
'type': 'TEXT_NUMBER',
'tag': ['GANTT_PERCENT_COMPLETE'],
'width': 85
}, {
'title': 'Assigned To',
'type': 'CONTACT_LIST',
'tag': ['GANTT_ASSIGNED_RESOURCE', 'GANTT_DISPLAY_LABEL'],
'width': 150
}, {
'title': '% Use',
'type': 'TEXT_NUMBER',
'tag': ['GANTT_ALLOCATION'],
'width': 60
}, {
'title': 'Days',
'type': 'DURATION',
'tag': ['GANTT_DURATION'],
'width': 70
}, {
'title': 'Start',
'type': 'ABSTRACT_DATETIME',
'tag': ['CALENDAR_START_DATE', 'GANTT_START_DATE'],
'width': 80
}, {
'title': 'Start',
'type': 'ABSTRACT_DATETIME',
'tag': ['CALENDAR_START_DATE', 'GANTT_START_DATE'],
'width': 80
}, {
'title': 'Finish',
'type': 'ABSTRACT_DATETIME',
'tag': ['CALENDAR_END_DATE', 'GANTT_END_DATE'],
'width': 80
}, {
'title': 'Type',
'type': 'TEXT_NUMBER',
'width': 150
}, {
'title': 'Comments',
'type': 'TEXT_NUMBER',
'width': 700
}
]
})
response = SS.Folders.create_sheet_in_folder(folder_id, resource_sheet)
new_sheet = response.result
return new_sheet
I am getting the following error code:
smartsheet.exceptions.ApiError: {"result": {"shouldRetry": false,
"code": 1142, "name": "ApiError", "errorCode": 1142, "recommendation":
"Do not retry without fixing the problem. ", "message": "Column type
DURATION is reserved for project sheets and may not be manually set on
a column.", "refId": "6gurrzzwhepe", "statusCode": 400}}
Is there a way I can create project sheets from scratch?
I have tried setting gantt_enabled to true but that just triggered a different error, so did setting 'project_settings'.
I have tried creating the sheet with just the primary column, then update_sheet to set project settings, which tells me: To set projectSettings, you must first enable dependencies on the sheet.
I have tried setting dependencies enabled, both directly in the create_sheet and in update_sheet, but both return: The attribute(s) sheet.dependenciesEnabled are not allowed for this operation.
I'm going to keep trying things, but I'm getting out of ideas.